In preparation for the excavation phase of the BCIT TTSH Project, Parking Lot K will be closed. The General Contractor will use the site for the layover area for tracks.
- Coinciding with the Lot K closure, two short sections of the walking path currently used to access the lot will also be closed, (one path located north of Lot K and one east of Lot K).
- An alternative route will be signed.
- During the closure, the Parking Kiosk and Emergency Call Station will remain active and accessible to patrons.
Closure Period: October 10, 2022 – Fall 2024
Plan of the Closures
Over the next month construction work will be taking place in the areas around parking Lot7. This is a preparatory work for the South Campus Infrastructure project.
The work will be in 4 phases starting on October 21 and continuing until November 18. A small number of parking spaces will be closed. As the work zones move South the closures will be adjusted.
Work Zones
- Zone 1: Mon 21 Oct – Tue 29 Oct (Mobilization begins October 21 with closure in place October 28-29).
- Zone 2: Wed 30 Oct – Fri 01 Nov
- Zone 3: Mon 04 Nov – Thu 07 Nov
- Zone 4: Sat 09 Nov
Zone 1
Mon 21 Oct – Tue 29 Oct
- Mobilization begins October 21: Roper Avenue will be closed during October 21 only
- Roper Avenue will be closed on October 28-29.
- Drivers will be rerouted through Lot 7 with flaggers and signage in place
- Seven parking spaces in Lot 7 will be out of commission.
Zone 2
- Access to parking lot 7 from Roper Ave and Ford Ave will be available with signage and flagger in place.
- Approximately 27 parking stalls to be closed for this phase and re-opened when complete.
Zone 3
- Access to parking lot 7 from Roper Ave and Ford Ave will be available with signage and flagger in place.
- Approximately 11 parking stalls to be closed for this phase and re-opened when complete.
Zone 4
- Pedestrians from the “EVO” parking stalls will be provided an alternate route through parking lot D/F
- No parking stalls to be closed for this phase